TestA run TestB

General chat about HostMonitor
Post Reply
TalT
Posts: 6
Joined: Sun Aug 10, 2008 10:08 am

TestA run TestB

Post by TalT »

How can I make TestB run upon TestB completion?
KS-Soft
Posts: 12821
Joined: Wed Apr 03, 2002 6:00 pm
Location: USA
Contact:

Post by KS-Soft »

I think you should use "This test depends on another test(s)" option
http://www.ks-soft.net/hostmon.eng/mfra ... htm#Master

Regards
Alex
TalT
Posts: 6
Joined: Sun Aug 10, 2008 10:08 am

Post by TalT »

In this case TestB will run with his own defined schedule. The “problem” I’m trying to solve is as followed: TestA complete with “green” statusTestB starts regardless of his schedule.
KS-Soft
Posts: 12821
Joined: Wed Apr 03, 2002 6:00 pm
Location: USA
Contact:

Post by KS-Soft »

You have send e-mail as well, so we sent reply to you e-mail address

Regards
Alex